Orsted puts up $100M guarantee that it will build New Jersey’s first offshore wind farm by 2025
View
Date:2025-04-18 08:22:41
OCEAN CITY, N.J. (AP) — The Danish wind energy company Orsted has put up a $100 million guarantee that it will build New Jersey’s first offshore wind farm.
But it will lose that money if the project is not operating by Dec. 2025 — a year after the deadline approved by state utility regulators.
New Jersey’s Board of Public Utilities approved an agreement Wednesday with Orsted under which the company would forfeit the money if the project is not up and running within 12 months of a series of deadlines previously ordered by the board.
Those deadlines call for the project to reach commercial operation in stages by May 1, Sept. 1 and Dec. 1, 2024. But it would forfeit the guarantee money if the project is not operational by December 2025.
The money put up on Oct. 4 by Orsted and placed in an escrow account was required under the terms of a law Gov. Phil Murphy signed in July allowing Orsted to keep federal tax credits that it otherwise would have had to return to New Jersey ratepayers.
The Democratic governor, who wants to make New Jersey the East Coast hub of the nascent offshore wind industry, said the tax break was needed. He said it would help Orsted complete the project in the face of financial challenges buffeting the industry. which also faces substantial political opposition, mostly from Republican legislators and their supporters.
As an example, on Thursday, New York regulators rejected a request from companies for larger subsidies to complete large-scale wind, solar and offshore wind projects, saying the expected the companies to abide by the terms of their deals with the state.
Orsted said in a statement that Wednesday’s approval by the New Jersey utilities board “continues the process of complying with the statutory requirements outlined in legislation signed by Governor Murphy earlier this year.”
But it did not address its own timetable for completing the first of two offshore wind projects it plans to build off the New Jersey coast.
In August, Orsted said the project would be delayed until 2026 due to supply chain issues, higher interest rates, and a failure so far to garner enough tax credits from the federal government.
The company said during an earnings conference call that it could be forced to write off about $2.3 billion on U.S. projects that are worth less than they had been. It also said it had considered simply abandoning the Ocean Wind I project off the southern New Jersey coast, but decided for the time being to stick with it.
The company did not respond to repeated requests Wednesday and Thursday for clarification of its timetable for the project. Its web site says only, “The project is scheduled to become operational in 2025, with final commissioning in 2026.”
An affidavit filed with the board last month by David Hardy, CEO of Boston-based Orsted North America, committed the company to carrying out the project once the board approved the guarantee, which was done on Wednesday.
“I can affirm that Ocean Wind I shall complete and operate the Ocean Wind I approximate 1,100-megawatt qualified offshore wind project,” he wrote.
Orsted has federal approval for the Ocean Wind I project, and has state approval for a second New Jersey project, Ocean Wind II. Under Wednesday’s agreement, the company would get its $100 million back if it does not receive all the government approvals it needs to build and operate the first project.
If Orsted forfeits the money, it could be returned to New Jersey utility ratepayers.
___
Follow Wayne Parry on X, formerly known as Twitter, at www.twitter.com/WayneParryAC
veryGood! (93)
Related
- Trump's 'stop
- Girl dinner, the Roman Empire: A look at TikTok's top videos, creators and trends of 2023
- Multiple injuries reported in nighttime missile attack on Ukrainian capital
- Plaintiffs in a Georgia redistricting case are asking a judge to reject new Republican-proposed maps
- Alex Murdaugh’s murder appeal cites biased clerk and prejudicial evidence
- German government reaches solution on budget crisis triggered by court ruling
- Watch as rush-hour drivers rescue runaway Chihuahua on Staten Island Expressway
- Newly elected progressive Thai lawmaker sentenced to 6 years for defaming monarchy
- Skins Game to make return to Thanksgiving week with a modern look
- North Carolina officer who repeatedly struck woman during arrest gets 40-hour suspension
Ranking
- 'Most Whopper
- 2023 in other words: AI might be the term of the year, but consider these far-flung contenders
- Punter Matt Araiza to be dropped from rape lawsuit as part of settlement with accuser
- Amid outcry over Gaza tactics, videos of soldiers acting maliciously create new headache for Israel
- Dick Vitale announces he is cancer free: 'Santa Claus came early'
- Punter Matt Araiza to be dropped from rape lawsuit as part of settlement with accuser
- Wildfires can release the toxic, cancer-causing 'Erin Brockovich' chemical, study says
- Two beloved Christmas classics just joined the National Film Registry
Recommendation
Nevada attorney general revives 2020 fake electors case
North Korean and Russian officials discuss economic ties as Seoul raises labor export concerns
'We will do what's necessary': USA Football CEO wants to dominate flag football in Olympics
NFL power rankings Week 15: How high can Cowboys climb after landmark win?
Alex Murdaugh’s murder appeal cites biased clerk and prejudicial evidence
Former Iowa police officer sentenced to 15 years for exploiting teen in ride-along program
Semi-trailer driver dies after rig crashes into 2 others at Indiana toll plaza
Man arrested in Washington state after detective made false statements gets $225,000 settlement